Where does PATH400 actually let you off in the middle of Buckhead? The trail now has nearly five open miles in Buckhead, linking neighborhoods, parks, businesses and four MARTA stations. For most of that distance it runs alongside GA-400, near Peachtree Road. Denise Starling, executive director of Livable Buckhead, says the commercial core and the southern trail "sit frustratingly close to one another without actually connecting."
This fall, two of the missing pieces were finished. Several more have dates in 2027 and 2028. The long runs are mostly done. The stretches still missing are measured in fractions of a mile, and they cost the most money and take the most time.
The Boardwalk gives the trail a finished route to Peachtree Road
In late September, the Buckhead Community Improvement District declared the Lenox Boardwalk finished and open, Urbanize Atlanta reported. The Boardwalk is 0.44 miles long and runs along Lenox Road from MARTA's Lenox station at East Paces Ferry Road to Peachtree Road. It has an elevated path 10 to 12 feet wide, brighter pedestrian lighting, new traffic signal mast arms and partial tree shade. The project cost $15.6 million.
The Boardwalk matters because of where it starts. PATH400's East Paces Ferry Spur already linked the Gordon Bynum Bridge to Lenox station. The Boardwalk picks up at that same station. You can now walk from the trail at Gordon Bynum Bridge, past Lenox station, and along the new path to Peachtree Road at Lenox Square, all on dedicated walking routes. Buckhead CID describes the result as a "safer, more direct connection between the Lenox MARTA station, Lenox Square, and the surrounding retail, hospitality and business community."
The width was a deliberate choice. Jim Durrett, executive director of Buckhead CID, told 11Alive that the Boardwalk is meant for "people to be able to enjoy sitting down and having a visit, a cup of coffee, a sandwich, something like that, while also having room for people to walk and bike and ride scooters adjacent to that." He added that everything the district designs "is going to be generous and not just a five or six foot sidewalk for people." Buckhead CID also calls the Boardwalk the "design standard for the two sections still to come."
The other project declared finished sits a mile or so north, where Wieuca Road meets Phipps Boulevard. Buckhead CID calls it Atlanta's first multi-lane roundabout. It has bike lanes, crosswalks, a multi-use pathway and placemaking signage. An 85-foot landscaped island replaced an asphalt expanse the size of a small parking lot, at what the district considers one of Buckhead's busiest intersections. The City of Atlanta and Buckhead CID split the $4 million cost.
A route you can walk this weekend, south to north
The finished pieces add up to a usable route, as long as you know where to get on and where to leave the car. Going north, the access points are:
- Mile 0, at Garson Drive and Piedmont Road. This is PATH400's southern anchor, with free street parking on Adina Drive. Lindbergh Center is the MARTA station the PATH400 map shows at this end of the trail.
- Miami Circle. The trail passes directly by Eclipse di Luna at 764 Miami Circle, which advertises parking for diners.
- The "Great Blue" mural and the Gordon Bynum Bridge. This is where PATH400's southern section begins. The map also marks it as the Lenox Square access point.
- The East Paces Ferry Spur to Lenox station, where the new Boardwalk continues to Peachtree Road.
- Lenox Road at the BUCKHEAD wall, at GA-400. You can park free at The Prominence, 3475 Piedmont Road NE, during trail hours. According to the PATH400 FAQ, you take a visitor ticket and tell the exit attendant you are using the trail.
- Old Ivy Park. It has its own parking on Old Ivy Road, underneath GA-400.
- Wieuca Road and Mountain Way Common. Starling calls the treetop bridge at Mountain Way Common the trail's "treetop experience."
- Loridans Drive. For now the open trail ends here, and the active construction zone starts.
Livable Buckhead says the open sections will stay open. Near active work areas, watch for construction signs and occasional temporary closures.
What's left is short, slow and expensive
The list above has two breaks you can't walk across yet. One is between Peachtree Road and the Gordon Bynum Bridge. The other is the crossing at Lenox Road and GA-400. Both are short. Here is the schedule for every remaining gap.
| Missing piece | Size or cost | Where it stands | Expected timing |
|---|---|---|---|
| PATH400 north of Loridans Drive | Part of a ~7.4-mile continuous trail once open | Concrete, grading, handrails, landscaping underway | Q1 2027 per Livable Buckhead; ATLDOT lists April 9, 2027 |
| Peachtree Park connection | A "short section" | In city procurement | Construction early 2027, done later that year |
| Southern Beltline link | Widened sidewalks, new signs and pavement markings | In city procurement | Construction early 2027, done later that year |
| Lenox Road phase two, Peachtree Road to Phipps Boulevard | About $10 million | Final engineering, then right-of-way and permitting | Groundbreaking in 2027 |
| Lenox Road phase three bridge over GA-400 | 0.62 miles, $40 to $56 million | Active design | Groundbreaking in 2028 |
The Peachtree Park connection will leave Peachtree Road between the InterContinental Buckhead Atlanta and the Embassy Suites. It will pass briefly through the Peachtree Park neighborhood and meet the Gordon Bynum Bridge. Starling sums up why such a short piece gets so much attention:
"The Peachtree Park connection is not long, but it is exactly the kind of small gap with an outsized ability to annoy us."
The bridge is the bigger delay. At its intersection with Lenox Road, the Buckhead Loop roadway reaches 10 lanes wide. Buckhead CID describes the planned bridge as a "first-of-its-kind elevated pedestrian and bicycle bridge" that will close "one of Buckhead's hardest gaps for anyone not in a car." Earlier projections had construction starting in 2027. The latest update moves the groundbreaking to 2028. A $10 million federal grant covers part of the cost. The cost difference is large. The bridge covers about 50 percent more distance than the Boardwalk, which cost $15.6 million, and its estimate is roughly three times as high.
Durrett explained to 11Alive why a bridge is needed at all. "We have to do bridges because you can't cross on certain interchanges safely because of the way that the roads have been designed and how much traffic they accommodate," he said. In the same interview, around November 2025, he said the bridges are being designed as the entrance to HUB404, the planned park capping GA-400. That project is "on hold right now because it requires federal funding, and there's no appetite for that sort of investment today in Washington." The bridge is moving forward on its own funding plan, with a gateway built for a park that has no schedule.
North of Loridans, the long stretch is moving faster
The northern extension is the one remaining piece that is long. It is also the closest to finished. Starling describes the terrain as "trail building on hard mode," with huge retaining walls, steep grades and a large switchback. Planting will wait for cooler weather. Sandy Springs has prioritized its section from the Atlanta city limits to Windsor Parkway so both cities can open together. A joint celebration is planned once the construction schedule is firm. Together the sections will give about 7.4 continuous miles of PATH400 heading toward the Perimeter area.
Livable Buckhead expects construction on the Atlanta section to finish in the first quarter of 2027. ATLDOT's project page lists a construction finish date of April 9, 2027. Starling notes that the actual opening also depends on final inspections, landscaping and coordination with Sandy Springs.
Other connections are further out. Links west to Blue Heron Nature Preserve and later to Chastain Park are still in the planning, partnership and funding stage. So is a direct connection from Lenox Road at the BUCKHEAD wall to Peachtree Road, which will start with a new plan developed alongside Buckhead CID and commercial property owners.
Fall dates along the route
The southern stretch near Miami Circle has the busiest fall calendar. Livable Buckhead's annual fundraiser, Party on the PATH, was set for Sunday, October 4, 5:30 to 9 p.m., at Eclipse di Luna, with a VIP reception at Johnson Lowe Gallery. Livable Buckhead also lists a free Miami Circle Gallery Stroll on November 21, 4 to 7 p.m., with more than 10 galleries open along Miami Circle.
One more walk is coming off the trail network. Atlanta bought the 30-acre Lucinda Bunnen forest off Randall Mill Road for $15 million, with half the money coming from the city's Tree Trust Fund and half from private donations, and Rough Draft Atlanta reports that the city says public trails there could open as early as 2027.
Whether a home sits a few blocks from a finished trail access point or along a route still waiting on 2027 construction can affect how it is presented and priced. Tommy Nguyen follows these Buckhead projects block by block. To see where your home stands today, start with an instant home valuation.